File #: 0661-20    Version: 1 Name: Change Order No. 2 Manchester Willard St Lagco, Inc.
Type: Resolution Status: Approved
File created: 6/25/2020 In control: Urban County Council
On agenda: 7/9/2020 Final action: 7/9/2020
Enactment date: 7/9/2020 Enactment #: R-348-2020
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with LAGCO, Inc., for the Manchester Street and Willard Street Sanitary Sewer Improvements Project, increasing the Contract price by the sum of $118,100, from $2,162,730 to $2,280,830, and extending the date of completion to July 3, 2020. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. CO1 Area Map, 4. 00689276.pdf, 5. R-348-2020, 6. Contract # 225-2019

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with LAGCO, Inc., for the Manchester Street and Willard Street Sanitary Sewer Improvements Project, increasing the Contract price by the sum of $118,100, from $2,162,730 to $2,280,830, and extending the date of completion to July 3, 2020. [Div. of Water Quality, Martin]

Summary

Authorization to execute a Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order #2 to the Agreement with Lagco, Inc., for the Manchester Street and Willard Street Sanitary Sewer Improvements Project, increasing the Contract price by the sum of $118,100.00, from $2,162,730.00 to $2,280,830.00, and extending the date of completion to July 3, 2020. Funds are Budgeted. [L0661-20] [Martin/Albright]

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 6/25/20]}

Risk Management:  {No}

Fully Budgeted [select]: Yes

Account Number:                     4003-303408-3468-92811

This Fiscal Year Impact:                     $118,100.00

Annual Impact:                      $

Project: MANCHESTER_2020

Activity: CONSTRUCT

Budget Reference: 2020

Current Balance: $246,702.50

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Agreement with Lagco, Inc., for the Manchester Street and Willard Street Sanitary Sewer Improvements Project, increasing the contract price by the sum of $118,100.00, from $2,162,730.00 to $2,280,830.00, and extending the date of completion to July 3, 2020.

                     Section 2 - That an amount, not to exceed the sum of $118,100.00, be and hereby is approved for payment to Lagco, Inc., from account #4003 - 303408 - 92811, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL: