File #: 0677-22    Version: 1 Name: Town Branch Phase 6 Change Order No. 4
Type: Resolution Status: Approved
File created: 6/24/2022 In control: Urban County Council
On agenda: 7/7/2022 Final action: 7/7/2022
Enactment date: 7/7/2022 Enactment #: R-400-2022
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Four (4) to the Agreement with L-M Asphalt Partners d/b/a ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $194,604.26 and raising the total Contract price from $4,438,505.01 to $4,633,109.27. [Div. of Engineering, Burton]
Attachments: 1. 22-Blue Sheet ATS CO No. 4, 2. Concept Map, 3. LFUCG CO No. 4 - TBT 6 (Partial Signatures)), 4. 00759964.pdf, 5. R-400-2022, 6. Contract #003-2020 Change Order #4

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Four (4) to the Agreement with L-M Asphalt Partners d/b/a ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $194,604.26 and raising the total Contract price from $4,438,505.01 to $4,633,109.27. [Div. of Engineering, Burton]

 

Summary

Authorization to execute Change Order No. 4 with ATS Construction for the Town Branch Trail Phase 6, increasing the Contract price by the sum of $194,604.26 from $4,438,505.01 to 4,633,109.27, to construct additional parking along the trail at 1265 Manchester Street. Funds are Budgeted. (L0677-22) (Burton/Albright)

 

Budgetary Implications: Yes

Advance Document Review:

Law: Yes, Brittany Smith, 06/23/22

Risk Management:  N/A

Fully Budgeted: YES

Account Number: 3160-303202-3225-90313

 

This Fiscal Year Impact: $194,604.26

Annual Impact:   $

Project: TOWN_TGER_2017

Activity: CONST

 

Budget Reference: 2017

Current Balance:$ 812,846.13

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
Four (4), which is attached hereto and incorporated herein by reference, to the Agreement with L-M Asphalt Partners, d/b/a ATS Construction, for the Town Branch Trail Phase 6, increasing the Contract price by $194,604.26 and raising the total Contract price from $4,438,505.01 to $4,633,109.27.

                     Section 2 - That an amount, not to exceed the sum of $194,604.26, is hereby authorized for payment to L-M Asphalt Partners, d/b/a ATS Construction, from account # 3160-303202-90313, pursuant to the terms of Change Order Four (4).

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

                                                                                                                                                   ______________________________

                                                                                                                                                   MAYOR

 

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

0677-22:BGS:X:\CASES\COMDEV\22-LE0003\LEG\00759964.DOCX