File #: 0754-25    Version: 1 Name: Phoenix Reimagined Change Order 6
Type: Resolution Status: Approved
File created: 8/8/2025 In control: Urban County Council
On agenda: 8/28/2025 Final action: 8/28/2025
Enactment date: 8/28/2025 Enactment #: R-400-2025
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Six (6) to the Agreement with Haire Construction, LLC, for the Phoenix Park Reimagined Project, increasing the Contract price by $74,885.25 and raising the total Contract price to $3,355,398.91. [Div. of Parks and Recreation, Conrad]
Attachments: 1. Phoenix Park Reimagined Memo Signed - Corrected, 2. Phoenix Park Reimagined - Change Order #6 - Corrected, 3. RESO 0754-25 4929-8557-4498 v.1.pdf, 4. R-400-2025

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Six (6) to the Agreement with Haire Construction, LLC, for the Phoenix Park Reimagined Project, increasing the Contract price by $74,885.25 and raising the total Contract price to $3,355,398.91. [Div. of Parks and Recreation, Conrad]

 

Summary

Authorization to execute Change Order #6 with Haire Construction LLC in increase the original scope to include the construction and installation of a new park sign for Phoenix Park. The increased amount is $74,885.25, bringing the new Contract total to $3,355,398.91. Funds are Budgeted. (L0754-25)(Conrad/Ford)

 

Budgetary Implications [select]: Yes

Advance Document Review:

Law: No

Risk Management:  No

Fully Budgeted [select]: Yes

Account Number:                      2614-707602-7221-91015                     $32,385.25

1105-707602-7221-91015                     $42,500.00

 

This Fiscal Year Impact: $74,885.25 

Annual Impact:

Project:                      PHOENIX_PK_2024

DISTRICT03_2024

Activity:

Budget Reference:

Current Balance: encumbered

 

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 – That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.
Six (6), which is attached hereto and incorporated herein by reference, to the Agreement with Haire Construction, LLC, for the Phoenix Park Reimagined Project, increasing the contract price by $74,885.25 and raising the total contract price to $3,355,398.91.

                     Section 2 – That an amount, not to exceed the additional sum of $74,885.25, is hereby authorized for payment to Haire Construction, LLC, from account # 2614-707602-7221-91015 and account # 1105-707602-7221-91015, pursuant to the terms of Change Order Six (6).

                     Section 3 – That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 