File #: 0323-13    Version: 1 Name: Change Order #3 Expansion Area 2A
Type: Resolution Status: Approved
File created: 4/1/2013 In control: Urban County Council
On agenda: 4/25/2013 Final action: 4/25/2013
Enactment date: 4/25/2013 Enactment #: R-177-2013
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three to the Contract with GRW Engineers, Inc., for the investigation and design of the Expansion Area 2A Pumping Station and Force Main, increasing the contract price by the sum of $37,840 from $462,350 to $500,190. [Div. of Water Quality, Martin]
Attachments: 1. Updated Blue Sheet Memo, 2. Contract History Form, 3. 00385490.pdf, 4. Resolution 177-2013.pdf
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. Three to the Contract with GRW Engineers, Inc., for the investigation and design of the Expansion Area 2A Pumping Station and Force Main, increasing the contract price by the sum of $37,840 from $462,350 to $500,190. [Div. of Water Quality, Martin]
Summary
Authorization to execute  Change Order No. 3 to agreement with GRW Engineers, Inc., for the Investigation and Design for Expansion Area 2A Pumping Station and Force Main.  (L0323-13)  (Martin/Moloney)
This is a request to execute Change Order No. 3 to agreement with GRW Engineers, Inc., for an amount not to exceed $37,840 for the Investigation and Design for Expansion Area 2A Pumping Station and Force Main.  This increase brings the total new project cost to $500,190.  Funds are budgeted.  
 
Budgetary Implications: YES
Advance Document Review: Law/Risk Management
Fully Budgeted: YES            
Account Number:  4003-303401-3424-92811
This Fiscal Year Impact: $37,840
Annual Impact:       $0.00
Project: 2AEXPANSI_2010
Activity: CONSTRUCT
Budget Reference: 2010
Current Balance: $3,466,090.64
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
      Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No.  Three, which is attached hereto and incorporated herein by reference, to GRW Engineers, Inc., for the investigation and design of the expansion area 2A pumping station and force main, increasing the contract price by the sum of $37,840.00 from    $462,350.00 to $500,190.00.
      Section 2 - That an amount, not to exceed the sum of $37,840.00, be and hereby is approved for payment to GRW Engineers, Inc., from account # 4003-303401-92811, pursuant to the terms of the Change Order.
      Section 3 - That this Resolution shall become effective on the date of its passage.
      PASSED URBAN COUNTY COUNCIL:
 
 