File #: 0145-26    Version: 1 Name: Change Order #2 - Terracon CO#2- LF00211709
Type: Resolution Status: Approved
File created: 2/13/2026 In control: Urban County Council
On agenda: 2/26/2026 Final action: 2/26/2026
Enactment date: 2/26/2026 Enactment #: R-060-2026
Title: A Resolution authorizing the Mayor or her designee, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Terracon, for Special Inspections associated with the new Senior and Therapeutic Center construction, increasing the Contract price by the sum of $13,870, from $50,305 to $64,175. [Dept. of General Services, Ford]
Attachments: 1. Terracon - CO2 - Memo, 2. Terracon - CO2 - Documentation for Change, 3. Terracon - CO2 - Justification for Change, 4. Terracon - CO2 - CO Details, 5. RESO 0145-26 4898-4769-5760 v.1.pdf, 6. R-060-2026

Title

A Resolution authorizing the Mayor or her designee, on behalf of the Urban County Government, to execute Change Order No. 2 to the Agreement with Terracon, for Special Inspections associated with the new Senior and Therapeutic Center construction, increasing the Contract price by the sum of $13,870, from $50,305 to $64,175. [Dept. of General Services, Ford]

 

Summary

Authorization to execute Change Order #2 with Terracon for Special Inspections associated with soil density testing related to the New Senior & Therapeutic Center construction in the amount of $13,870.00 increasing the Contract amount from $50,305.00 to $64,175.00. Funds are Budgeted. (L0145-26)(Ford)

 

Budgetary Implications [select]: Yes

Advance Document Review:

Law: N/A

Risk Management:  N/A

Fully Budgeted [select]: Yes

Account Number:          1105-606102-6051-71206

This Fiscal Year Impact:             $ 13,870

Annual Impact:              $0

Project: SENIOR_CTR_2023

Activity: DESIGN_CAP

Budget Reference: 2023

Current Balance: $235,367.71

Body

 

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

Section 1 - That the Mayor or her designee, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Agreement with Terracon, for special inspections associated with the New Senior & Therapeutic Center construction, increasing the contract price by the sum of $13,870.00, from $50,305.00 to $64,175.00.

                     Section 2 - That an amount, not to exceed the sum of $13,870.00, be and hereby is approved for payment to Terracon, from the following account 1105-606102-71206, pursuant to the terms of the Change Order.

Section 3 - That this Resolution shall become effective on the date of its passage.