File #: 0222-26    Version: 1 Name: Change Order Joyland Drainage Project
Type: Resolution Status: Approved
File created: 3/9/2026 In control: Urban County Council
On agenda: 3/26/2026 Final action: 3/26/2026
Enactment date: 3/26/2026 Enactment #: R-116-2026
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 5 (Final) to the Agreement with Lagco Inc., for Joyland Area Storm Drainage Project- Contract No. 365-2024, for the Div. of Water Quality, increasing the Contract by the sum of $104,952, from $1,182,126 to $1,287,078. [Div. of Water Quality, Martin]
Attachments: 1. Bluesheet Joyland CO #5 updated, 2. Changer Order Contract_, 3. RESO 0222-26 Change Order Joyland Drainage Project_ 4928-0365-8649 v.1.pdf, 4. R-116-2026

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 5 (Final) to the Agreement with Lagco Inc., for Joyland Area Storm Drainage Project- Contract No. 365-2024, for the Div. of Water Quality, increasing the Contract by the sum of $104,952, from $1,182,126 to $1,287,078. [Div. of Water Quality, Martin] 

 

Summary

Authorization to execute Final Change Order No.5 to the Agreement with Lagco Inc. increasing the Contract price by the sum of $104,954.31 from $1,182,126.00 to $1,287,080.31 for the Joyland Area Storm Drainage Project- Contract No. 365-2024. Budget amendment in process. (L0222-26)(Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law:  Yes  J. Todd Henning

Risk Management: No

Fully Budgeted [select]: Yes

Account Number:                     4052-303204-3334-92211

This Fiscal Year Impact:                     $104,954.31

Annual Impact:                      $

Project: JOYLAND_2021

Activity: CONSTRUCT

Budget Reference:

Current Balance: $104,954.31

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 5 (final), which is attached hereto and incorporated herein by reference, to the agreement with Lagco Inc., for Joyland Area Storm Drainage Project- Contract No. 365-2024, for the Division of Water Quality, increasing the contract price by the sum of $104,952.00, from $1,182,126.00 to $1,287,078.00.

                     Section 2 - That an amount, not to exceed the sum of $104,952.00, be and hereby is approved for payment to Lagco Inc., from accounts # 4052-303204-92211 and 4052-303204-71223, pursuant to the terms of the Change Order.

Section 3 - That this Resolution shall become effective on the date of its passage.

PASSED URBAN COUNTY COUNCIL:


________________________________

MAYOR

 

ATTEST:

 

______________________________________

CLERK OF URBAN COUNTY COUNCIL

0222-26:JTH:4928-0365-8649, v. 1