Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Contract Modification No. Two (2) to an Agreement with Palmer Engineering for additional design of Town Branch Trail Phase V, increasing the Contract price by the sum of $43,500 and raising the total Contract price from $696,502 to $740,002. [Div. of Engineering, Burton]
Attachments: 1. 22-Blue Sheet TB Trail VI CM No. 2, 2. 2022-5-26 TBT 5 CM No. 2 (Partial Signatures), 3. 2022-5-5 Area Map, 4. 00758644.pdf, 5. R-349-2022, 6. Contract #209-2015

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Contract Modification No. Two (2) to an Agreement with Palmer Engineering for additional design of Town Branch Trail Phase V, increasing the Contract price by the sum of $43,500 and raising the total Contract price from $696,502 to $740,002. [Div. of Engineering, Burton]

 

 

Summary

Authorization to execute Contract Modification No. 2 in the amount of $43,500.00 with Palmer Engineering for additional design of Town Branch Trail Phase V, increasing the total Contract price to $740,002.00. Funds are Budgeted. (L0600-22) (Burton/Albright)

 

Budgetary Implications]: Yes

Advance Document Review:

Law: Yes, Completed by Brittany Smith, 6/3/2022

Risk Management:  N/A

Fully Budgeted: Yes

Account Number: 3160-303202-3225-90313                     

This Fiscal Year Impact:                     $43,500

Annual Impact:                      

Project: TOWNBRNC_2015

Activity: V_DES_A

Budget Reference: 2015

Current Balance: $120,852.20

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Contract Modification No. Two (2) to the Agreement, which is attached hereto and incorporated herein by reference, with Palmer Engineering for additional design of Town Branch Trail Phase V, increasing the contract price by the sum of $43,500.00 and raising the total contract price from $696,502.00 to $740,002.00.

                     Section 2 - That an amount, not to exceed the sum of $43,500.00, be and hereby is approved for payment to Palmer Engineering from account #3160-303202-90313, pursuant to the terms of the Agreement and Contract Modification No. Two (2).

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                              ___________________________________

                                                                                                                              MAYOR

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

0600-22:BGS:X:\CASES\COMDEV\22-LE0003\LEG\00758644.DOCX