header-left
File #: 0669-22    Version: Name: Town Branch 5 Sub Drainage RFP# 27-2022
Type: Resolution Status: Approved
File created: 6/23/2022 In control: Urban County Council
On agenda: 7/7/2022 Final action: 7/7/2022
Enactment date: 7/7/2022 Enactment #: R-395-2022
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute an Engineering Services Agreement (awarded pursuant to RFP # 27-2022) with Stantec Consulting Services, Inc., for evaluation of the Town Branch 5 Sub Drainage Area, which includes the sanitary sewer service area for Remedial Measures Project TB-14, for the Div. of Water Quality, at a cost not to exceed $241,268. [Div. of Water Quality, Martin]
Attachments: 1. TB5 (Catapla RMP TB_14) blue sheet signed, 2. Task A - Sanitary, 3. Task A - Storm, 4. TB5 Project Area Map, 5. Catalpa Exhibit A Part One RFP27-2022, 6. Catalpa Exhibit A Part Two Addendum to RFP #27-2022, 7. Catalpa Exhibit B, 8. Catalpa Exhibit C, 9. Catalpa Exhibit D, 10. 00760070.pdf, 11. R-395-2022, 12. Contract #202-2022

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute an Engineering Services Agreement (awarded pursuant to RFP # 27-2022) with Stantec Consulting Services, Inc., for evaluation of the Town Branch 5 Sub Drainage Area, which includes the sanitary sewer service area for Remedial Measures Project TB-14, for the Div. of Water Quality, at a cost not to exceed $241,268. [Div. of Water Quality, Martin]

 

Summary

Authorization to execute a Contract, pursuant RFP No. 27-2022, with Stantec Consulting Services Inc. for evaluation of the Town Branch 5 Sub Drainage Area that includes the sanitary sewer service area for Remedial Measures Project TB-14, at a cost of $241,268.00. Funds are Budgeted. (L0669-22) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law:  Yes, Completed by Evan P. Thompson 6/21/2022

Risk Management No

Fully Budgeted [select]: Yes

Account Number: 4003-303408-3466-92811                     

This Fiscal Year Impact:                     $241,268.00

Annual Impact:                      $

Project: CATALPA

Activity: CONSENT_DE

Budget Reference: 2023

Current Balance: $500,000

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute an Engineering Services Agreement (awarded pursuant to RFP No. 27-2022), which is attached hereto and incorporated herein by reference, with Stantec Consulting Services, Inc., for evaluation of the Town Branch 5 Sub Drainage Area, which includes the sanitary sewer service area for Remedial Measures Project TB-14, at a cost not to exceed $241,268.00.

                     Section 2 - That an amount, not to exceed the sum of $241,268.00, be and hereby is approved for payment to Stantec Consulting Services, Inc. from account # 4003-303408-3466-92811, pursuant to the terms of the Agreement.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                              _______________________________

                                                                                                                              MAYOR

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

0669-22:EPT:X:\CASES\WATER-AIR\22-LE0003\LEG\00760070.DOCX