File #: 0363-16    Version: 1 Name: Truck Shed, Waste Management Change Order #2
Type: Resolution Status: Approved
File created: 3/31/2016 In control: Urban County Council
On agenda: 5/12/2016 Final action: 5/12/2016
Enactment date: 5/12/2016 Enactment #: R-258-2016
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Devere Construction, Inc., for the construction of a truck shed for the Div. of Waste Management, increasing the contract price by the sum of $22,386.75 from $756,607.61 to $778,994.36. [Div. of Waste Management, Thurman]
Attachments: 1. Memo 3-31-16, 2. Change Order, 3. 00530740.pdf, 4. RESOLUTION - 258-2016.pdf

Title

A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 2 to the Contract with Devere Construction, Inc., for the construction of a truck shed for the Div. of Waste Management, increasing the contract price by the sum of $22,386.75 from $756,607.61 to $778,994.36. [Div. of Waste Management, Thurman]

Summary

Authorization to approve Change Order #2 to Contract 219-2015 with Devere Construction, Inc., for the construction of a truck shed for the Division of Waste Management. This Change Order will allow for bird netting and a redesign of the lighting system and circuit for installation of a CCTV. The impact in FY 2016 will be $22,386.75. (L0363-15)(Hoskins-Squier)

Budgetary Implications: Yes

Advance Document Review:

Law: No

Risk Management:  No

Fully Budgeted: Yes

Account Number:                     1115-303501-0001-90512

This Fiscal Year Impact:                     $22,386.75

Annual Impact:                      $                     

Project:

Activity:

Budget Reference:

Current Balance: $146,733.94

Body

                     BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 2, which is attached hereto and incorporated herein by reference, to the Contract with Devere Construction, Inc., for the construction of a truck shed for the Division of Waste Management, increasing the contract price by the sum of $22,386.75 from $756,607.61 to $778,994.36.

                     Section 2 - That an amount, not to exceed the sum of $22,386.75, be and hereby is approved for payment to Devere Construction, Inc., from account #1115-303501-90512, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.