File #: 0453-13    Version: Name: Change Order No. 1 Haley Pike Landfill Closure Contract
Type: Resolution Status: Approved
File created: 4/30/2013 In control: Urban County Council
On agenda: 6/6/2013 Final action: 6/6/2013
Enactment date: 6/6/2013 Enactment #: R-266-2013
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Contract with R. B. Jergens Contractors, Inc., for the Haley Pike Landfill Closure, for the Dept. of Environmental Quality and Public Works, increasing the contract price by the sum of $484,075.29 from $2,250,895.35 to $2,734,970.64. [Dept. of Environmental Quality and Public Works, Moloney]
Attachments: 1. Memo Requesting Approval, Change Order Items, Haley Pike Landfill Closure, 2. Resolution - 453-13 (00390021).pdf, 3. Contract 176-2012.pdf, 4. Resolution 266-2013.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. One (1) to the Contract with R. B. Jergens Contractors, Inc., for the Haley Pike Landfill Closure, for the Dept. of Environmental Quality and Public Works, increasing the contract price by the sum of $484,075.29 from $2,250,895.35 to $2,734,970.64. [Dept. of Environmental Quality and Public Works, Moloney]
Summary
Authorization to execute Change Order No. 1 to Agreement with R. B. Jergens Contractors, Inc. for the Haley Pike Landfill Closure Contract 82-2012.  (L0453-13) (Moloney)
This is a request to execute Change Order No. 1 to Agreement with R. B. Jergens Contractors, Inc. in the amount of $484,075.29 for the Haley Pike Landfill Closure Contract 82-2012.  This increase brings the total new contract total to $2,734,970.64.  Funds are budgeted.
 
Budgetary Implications: Yes/NO
Advance Document Review: Law/Risk Management
Fully Budgeted: Yes
Account Number:      4121 303102 3063 90316
This Fiscal Year Impact:      $484,075.29
Annual Impact:       $
Project:
Activity:
Budget Reference:
Current Balance: $749,203.81
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
      Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. One (1), which is attached hereto and incorporated herein by reference, to the Contract with R. B. Jergens Contractors, Inc., for the Haley Pike Landfill Closure, for the Department of Environmental Quality and Public Works, increasing the contract price by the sum of $484,075.29 from $2,250,895.35 to $2,734,970.64.
      Section 2 - That an amount, not to exceed the sum of $484,075.29, be and hereby is approved for payment to R. B. Jergens Contractors, Inc., from account # 4121-303102-90316, pursuant to the terms of the Change Order.
      Section 3 - That this Resolution shall become effective on the date of its passage.