header-left
File #: 0479-21    Version: 1 Name: Change Order No. 3 (Final) ATS Construction EA3 Trunk Sewer Project
Type: Resolution Status: Approved
File created: 5/4/2021 In control: Urban County Council
On agenda: 6/10/2021 Final action: 6/10/2021
Enactment date: 6/10/2021 Enactment #: R-303-2021
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 (Final) to the Agreement with L-M Asphalt Partners ltd. d/b/a ATS Construction, for the Expansion Area 3 Trunk Sewer Project, increasing the Contract price by the sum of $240,779.59, from $4,476,870.65 to $4,717,650.24. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. EA 3 Trunk CO 3 Map, 4. 00726923.pdf, 5. R-303-20201, 6. Contract #227-2017
Related files: 0946-17

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 (Final) to the Agreement with L-M Asphalt Partners ltd. d/b/a ATS Construction, for the Expansion Area 3 Trunk Sewer Project, increasing the Contract price by the sum of $240,779.59, from $4,476,870.65 to $4,717,650.24. [Div. of Water Quality, Martin]

Summary

Authorization to execute Change Order No. 3 (Final) to the Agreement with L-M Asphalt Partners Ltd. d/b/a ATS Construction, for the Expansion Area 3 Trunk Sewer Project, increasing the Contract price by the sum of $240,779.59, from $4,476,870.65 to $4,717,650.24. Funds are Budgeted. (L0479-21) (Martin/Albright)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 05/04/21]}

Risk Management:  {No}

Fully Budgeted [select]: Yes

Account Number:                     4003-303408-3466-92811

This Fiscal Year Impact:                     $240,779.59

Annual Impact:                      $

Project: EA3TRK_2016

Activity: CONSENT_DE

Budget Reference: 2016

Current Balance: $397,583.82

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 3 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with L-M Asphalt Partners Ltd. d/b/a ATS Construction, for the Expansion Area 3 Trunk Sewer Project, increasing the Contract price by the sum of $240,779.59, from $4,476,870.65 to $4,717,650.24.

                     Section 2 - That an amount, not to exceed the sum of $240,779.59, be and hereby is approved for payment to L-M Asphalt Partners Ltd. d/b/a ATS Construction, from account #4003 - 303408 - 92811, pursuant to the terms of the Change Order.

                     Section 3 - That this Resolution shall become effective on the date of its passage.

                     PASSED URBAN COUNTY COUNCIL:

 

 

                                                                                                                              ______________________________

                                                                                                                              MAYOR

 

 

ATTEST:

 

________________________________

CLERK OF URBAN COUNTY COUNCIL

479-21:MSC:X:\Cases\WATER-AIR\21-LE0001\LEG\00726923.DOCX