header-left
File #: 1079-19    Version: 1 Name: Change Order No. 1 (Final) C3 Construction, LLC for Riviera Road Culvert Replacement
Type: Resolution Status: Approved
File created: 10/7/2019 In control: Urban County Council
On agenda: 11/14/2019 Final action: 11/14/2019
Enactment date: 11/14/2019 Enactment #: R-604-2019
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Agreement with C3 Construction, LLC, for the Riviera Rd. Culvert Replacement Project, increasing the contract price by the sum of $11,992.50, from $270,000.00 to $281,992.50, and extending the date of completion by sixty (60) calendar days, to September 6, 2019. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo, 2. LFUCG Contract Change Order, 3. Map, 4. 00669396.pdf, 5. RESOLUTION - 604-2019, 6. Contract #306-2018
Related files: 1223-18
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 (Final) to the Agreement with C3 Construction, LLC, for the Riviera Rd. Culvert Replacement Project, increasing the contract price by the sum of $11,992.50, from $270,000.00 to $281,992.50, and extending the date of completion by sixty (60) calendar days, to September 6, 2019. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No. 1 (Final) to the Agreement with C3 Construction, LLC for the Riviera Road Culvert Replacement Project, increasing the Contract price by the sum of $11,992.50 from $270,000.00 to $281,992.50, and extending the Contract completion date 60 calendar days, to September 6, 2019. Funds are Budgeted. (L1079-19) (Martin/Albright)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Yes, Completed by [Michael Cravens, 09/27/19]}
Risk Management: {No}
Fully Budgeted [select]: Yes
Account Number: 4052-303204-3334-92211
This Fiscal Year Impact: $11,992.50
Annual Impact: $
Project: STORM_REHAB
Activity: CONSTRUCT
Budget Reference: 2019
Current Balance: $122,447.73
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1 (Final), which is attached hereto and incorporated herein by reference, to the Agreement with C3 Construction, LLC, for the Riviera Road Culvert Replacement Project, increasing the Contract price by the sum of $11,992.50, from $270,000.00 to $281,992.50, and extending the date of completion by sixty (60) calendar days, to September 6, 2019.
Section 2 - That an amount, not to exceed the sum of $11,992.50, be and hereby is approved for payment to C3 Construction, LLC, from account # 4052 - 303204 - 92211, pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effectiv...

Click here for full text