File #: 0799-19    Version: 1 Name: Change Order #1 Blau Mechanical
Type: Resolution Status: Approved
File created: 8/1/2019 In control: Urban County Council
On agenda: 8/29/2019 Final action: 8/29/2019
Enactment date: 8/29/2019 Enactment #: R-455-2019
Title: A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Blau Mechanical, Inc. for the project Detention Plumbing 2019, replacing the domestic hot water lines, for the Div. of Community Corrections, increasing the Contract price by the sum of $40,468.41 from $172,000.00 to $212,468.41. [Div. of Community Corrections, Haney]
Attachments: 1. Memo Requesting Approval_Change Order.pdf, 2. Blau Change Order.pdf, 3. 00662921.pdf, 4. R-455-2019
Title
A Resolution authorizing and directing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Blau Mechanical, Inc. for the project Detention Plumbing 2019, replacing the domestic hot water lines, for the Div. of Community Corrections, increasing the Contract price by the sum of $40,468.41 from $172,000.00 to $212,468.41. [Div. of Community Corrections, Haney]


Summary
Authorization to approve Change Order #1 with Blau Mechanical (R206-2019) for the project Det_Plumbg_2019, replacing the domestic hot water lines at the Division of Community Corrections. The change is being requested to furnish and install a new mixing valve and station, and install additional piping. Increasing the Contract by $40,468.41 for a total of $212,468.41. Funds are Budgeted. (L0799-19) (Haney/Armstrong)


Budgetary Implications [select]: Yes
Advance Document Review:
Law: No, Completed by :
Risk Management: No
Fully Budgeted : Yes
Account Number: 2609-505401-5411-90511
This Fiscal Year Impact: $ 40,468.41
Annual Impact: $ 0
Project: DET_PLUMBG_2019
Activity: Construction
Budget Reference: 2019
Current Balance: $156,492
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized and directed to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Blau Mechanical, Inc., for the project Det_Plumbg_2019, replacing the domestic hot water lines for the Division of Community Corrections, increasing the Contract price by the sum of $40,468.41 from $172,000.00 to $212,468.41
Section 2 - That an amount, not to exceed the sum of $40,468.41, be and hereby is approved for payment to Blau Mechanical, Inc., from account: #2609-505401-5411-90511, pursuant to the terms of the Change Order.