File #: 0237-19    Version: 1 Name: Request Council authorization to execute Contract Modification No. 1 with Integrated Engineering, increasing their fee by $61,117 for design of the Armstrong Mill Road Sidewalk Project.
Type: Resolution Status: Approved
File created: 2/25/2019 In control: Urban County Council
On agenda: 3/21/2019 Final action: 3/21/2019
Enactment date: 3/21/2019 Enactment #: R-148-2019
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Contract Modification No. 1 to the Agreement with Integrated Engineering, PLLC, for design of the Armstrong Mill Sidewalk Project, increasing the Contract price by the sum of $61,117, from $120,999 to $182,116. [Div. of Engineering, Burton]
Attachments: 1. 19 - bluesheet memo, 2. Armstrong Mill CM #1 (Approved Fee Proposal), 3. Contract History CM#1 - Armstrong Mill, 4. CM #1 Form - Armstrong Mill, 5. 00646507.pdf, 6. RESOLUTION - 148-2019, 7. 018-2018 - CONTRACT
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Contract Modification No. 1 to the Agreement with Integrated Engineering, PLLC, for design of the Armstrong Mill Sidewalk Project, increasing the Contract price by the sum of $61,117, from $120,999 to $182,116. [Div. of Engineering, Burton]

Summary
Authorization to execute Contract Modification No. 1 with Integrated Engineering, increasing their fee by $61,117 for design of the Armstrong Mill Road Sidewalk Project. The scope of the design is being increased to include a pedestrian bridge crossing Landsdowne Drive Tributary on the south side of Armstrong Mill Rd. and a signal at the intersection of Armstrong Mill Road and Greentree Road. Details of the change are shown on the Contract Modification form. Budget amendments are in process. (L0237-19) (Burton/Hamilton)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: No
Risk Management: No
Fully Budgeted [select]: Budget Amendments 9867 and 9868 are in progress
Account Number: 3160-303202-3251-91715
This Fiscal Year Impact: $61,117
Annual Impact: $
Project: ARMSTRONG_2017
Activity: DESIGN
Budget Reference:
Current Balance: $9,001.00 (two BA's in process)
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Contract Modification No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Integrated Engineering, PLLC, for design of the Armstrong Mill Sidewalk Project, increasing the contract price by the sum of $61,117.00, from $120,999.00 to $182,116.00.
Section 2 - That an amount, not to exceed the sum of $61,117.00, be and hereby is approved for payment to Integrated Engineering, PLLC, from account # 3160-303202-91715, pursuant to the terms of the Contract Modification.
Section 3 - That this Resolution sh...