File #: 1149-18    Version: 1 Name: Change Order #1 - Bri Den CO#1 - 100-2018
Type: Resolution Status: Approved
File created: 10/22/2018 In control: Urban County Council
On agenda: 11/15/2018 Final action: 11/15/2018
Enactment date: 11/15/2018 Enactment #: R-699-2018
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Contract with Bri-Den Roofing, a Tecta America Co., LLC, for the Police Training Center Roof Replacement Project, increasing the Contract price by the sum of $737.84 from $259,000.00 to $259,737.84. [Div. of Facilities and Fleet Management, Baradaran]
Attachments: 1. Memorandum - Bri Den CO#1 CO#1 - 100-2018, 2. Change Order #1 - Bri Den - 100-2018, 3. Justification for Change - Bri Den CO#1 - 100-2018, 4. Documentation for Change - Bri Den CO#1 - 100-2018, 5. 00632609.pdf, 6. RESOLUTION - 699-2018, 7. 257-2018 -- CONTRACT
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Contract with Bri-Den Roofing, a Tecta America Co., LLC, for the Police Training Center Roof Replacement Project, increasing the Contract price by the sum of $737.84 from $259,000.00 to $259,737.84. [Div. of Facilities and Fleet Management, Baradaran]

Summary
Authorization to Execute Change Order #1 with Bri Den Roofing, A Tecta America Co. in the amount of $737.84 and an additional zero (0) working days to the schedule for the Roof Replacement at Police Training Center Contract #100-2018. The new Contract amount including this Change Order is $259,737.84. Funds are Budgeted. (L1149-18) (Baradaran/Hamilton)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: N/A
Risk Management: N/A
Fully Budgeted [select]: Yes
Account Number: 2607-707201-0001-76101
This Fiscal Year Impact: $737.84
Annual Impact: N/A
Project: FACILITY_2017
Activity: BUILD_IMPR
Budget Reference: 2017
Current Balance: $198,976.90
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Contract with Bri-Den Roofing, a Tecta America Company, LLC, for the Police Training Center Roof Replacement Project, increasing the Contract price by the sum of $737.84 from $259,000.00 to $259,737.84.
Section 2 - That an amount, not to exceed $737.84, be and hereby is approved for payment to Bri-Den Roofing, a Tecta America Company, LLC, from account #2607-707201-0001-76101 pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.