Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 3 (Final) to the Agreement with Tribute Contracting & Consultants, LLC, for the UK Trunk A Sewer Improvements Project, decreasing the contract price by the sum of $322,049.53 from $2,767,032.00 to $2,444,982.47. [Div. of Water Quality, Martin]
Summary
Authorization to approve Final Adjusting Change Order #3 to Tribute Contracting & Consulting LLC, decreasing the cost of UK Trunk A Sewer Project by $322,049.53 from $2,767,032.00 to $2,444,982.47. (L0381-18) (Martin/Hoskins-Squier)
Budgetary Implications [select]: YES
Advance Document Review:
Law: {Yes, Completed by [Michael Cravens, 4/4/18]}
Risk Management: {No}
Fully Budgeted [select]: Yes (savings)
Account Number: 4003-303408-3466-92811
This Fiscal Year Impact: ($322,049.53)
Annual Impact: $
Project: UKTRUNKA_2014
Activity: CONSENT_DE
Budget Reference:
Current Balance:
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 3 (FINAL), which is attached hereto and incorporated herein by reference, to the Agreement with Tribute Contracting & Consultants, LLC, for the UK Trunk A Sewer Improvements Project, decreasing the Contract price by the sum of $322,049.53 from $2,767,032.00 to $2,444,982.47.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: