File #: 1302-17    Version: 1 Name: Change Order #1 West Hickman WWTP Electrical Shop Project
Type: Resolution Status: Approved
File created: 11/20/2017 In control: Urban County Council
On agenda: 12/7/2017 Final action: 12/7/2017
Enactment date: 12/7/2017 Enactment #: R-769-2017
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Olympic Construction, LLC for the West Hickman Waste Water Treatment Plant Electrical Shop Project, increasing the contract price by the sum of $21,606.82 from $294,800.00 to $316,406.82, and extending the date of completion by thirty (30) calendar days, to January 26, 2018. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo.pdf, 2. Contract Change Order.pdf, 3. Change Order No. 1 Backup Documents.pdf, 4. WH WWTP Electrical Shop Map.pdf, 5. 00593512.pdf, 6. RESOLUTION - 769-2017.pdf, 7. 166-2017 - CONTRACT.pdf
Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Agreement with Olympic Construction, LLC for the West Hickman Waste Water Treatment Plant Electrical Shop Project, increasing the contract price by the sum of $21,606.82 from $294,800.00 to $316,406.82, and extending the date of completion by thirty (30) calendar days, to January 26, 2018. [Div. of Water Quality, Martin]
Summary
Authorization to execute Change Order No. 1 with Olympic Construction, LLC for the West Hickman Waste Water Treatment Plant Electrical Shop Project increasing the Contract price by the sum of $21,606.82 to $316,406.82, and extending the Contract term 30 calendar days from December 27, 2017 to January 26, 2018. Funds are Budgeted. (L1302-17) (Martin/Hoskins-Squier)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Select Yes, Completed by [Michael Cravens, 11/20/17]}
Risk Management: {Select No]}
Fully Budgeted [select]: Yes
Account Number: 4003-303401-3401-92711
This Fiscal Year Impact: $21,606.82
Annual Impact: $0
Project: WHWWTPELECSHOP
Activity: CONSTRUCT
Budget Reference: 2016
Current Balance: $45,200.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Agreement with Olympic Construction, LLC for the West Hickman Waste Water Treatment Plant Electrical Shop Project, increasing the Contract price by the sum of $21,606.82 from $294,800.00 to $316,406.82, and extending the date of completion by thirty (30) calendar days, to January 26, 2018.
Section 2 - That an amount, not to exceed the sum of $21,606.82, be and hereby is approved for payment to Olympic Construction, LLC, from account # 4003 - 303401 - 92711, pursuant to the terms of the C...