Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 1 to the Contract with Pearce Blackburn Roofing, LLC, for the Castlewood Community Center Roof Replacement Project, increasing the contract price by the sum of $9,874 from $183,420 to $193,294 and adding two (2) calendar days to the construction schedule. [Div. of Parks and Recreation, Conrad]
Summary
Authorization to execute Change Order No. 1 with Pearce-Blackburn Roofing in an amount of $9,874.00 for the Roof Replacement at Castlewood Community Center, Contract #46-2017. New Contract total is $193,294.00. Funds are Budgeted. (L0857-17) (Conrad/Reed)
Budgetary Implications: Yes
Advance Document Review:
Law: No
Risk Management: No
Fully Budgeted: Yes
Account Number: 2607-707601-7211-91018
This Fiscal Year Impact: $9,874.00
Annual Impact: N/A
Project: CASTLE_CTR_2017
Activity: ROOF
Budget Reference: 2017
Current Balance: $41,580.00
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 1, which is attached hereto and incorporated herein by reference, to the Contract with Pearce Blackburn Roofing, LLC, for the Castlewood Community Center Roof Replacement Project, increasing the Contract price by the sum of $9,874.00 from $183,420.00 to $193,294.00 and adding two (2) calendar days to the construction schedule.
Section 2 - That an amount, not to exceed $9,874.00, be and hereby is approved for payment to Pearce Blackburn Roofing, LLC, from account #2607-707601-7211-91018 pursuant to the terms of the Change Order.
Section 3 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL:
___________________________________
MAYOR
ATTEST:
________________________________
CLERK OF URBAN COUNTY COUNCIL