Title
A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 4 (final) to the Agreement with Judy Construction Co., for the Lower Cane Run Wet Weather Storage Facility Project, decreasing the Contract price by the sum of $700,259.43, from $12,078,360.00 to $11,378,100.57, and extending the date of completion by one hundred and twenty-two (122) days. [Div. of Water Quality, Martin]
Summary
Authorization to approve Final Adjusting Change Order No. 4 to Judy Construction Company decreasing the cost of the Lower Cane Run Wet Weather Storage Project by $700,259.43 from $12,078,360.00 to $11,378,100.57 and extending the contract completion date by 122 days. (L01021-18) (Martin)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Yes, Completed by [Michael Cravens, 9/20/18]}
Risk Management: {No}
Fully Budgeted [select]: Yes
Account Number: 4003-303408-3466-92811
This Fiscal Year Impact: -$700,259.43
Annual Impact: $
Project: LCRWWSTNK_2014
Activity: CONSENT_DE
Budget Reference: 2014
Current Balance:
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 4 (FINAL), which is attached hereto and incorporated herein by reference, to the Agreement with Judy Construction Company, for the Lower Cane Run Wet Weather Storage Facility Project, decreasing the Contract price by the sum of $700,259.43, from $12,078,360.00 to $11,378,100.57, and extending the date of completion by one hundred and twenty-two (122) days.
Section 2 - That this Resolution shall become effective on the date of its passage.
PASSED URBAN COUNTY COUNCIL: