File #: 1021-18    Version: 1 Name: Lower Cane Run Wet Weather Storage Change Order #4
Type: Resolution Status: Approved
File created: 9/21/2018 In control: Urban County Council
On agenda: 10/25/2018 Final action: 10/25/2018
Enactment date: 10/25/2018 Enactment #: R-623-2018
Title: A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 4 (final) to the Agreement with Judy Construction Co., for the Lower Cane Run Wet Weather Storage Facility Project, decreasing the Contract price by the sum of $700,259.43, from $12,078,360.00 to $11,378,100.57, and extending the date of completion by one hundred and twenty-two (122) days. [Div. of Water Quality, Martin]
Attachments: 1. Blue Sheet Memo.pdf, 2. LFUCG Contract Change Order.pdf, 3. Lower Cane Run Sanitary Sewers RMP Conrtact Change Order Form.pdf, 4. Change Order No.4 (Judy).pdf, 5. Map of Project Area.pdf, 6. 00629802.pdf, 7. RESOLUTION - 623-2018.pdf, 8. 191-2015- CONTRACT

Title

A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute Change Order No. 4 (final) to the Agreement with Judy Construction Co., for the Lower Cane Run Wet Weather Storage Facility Project, decreasing the Contract price by the sum of $700,259.43, from $12,078,360.00 to $11,378,100.57, and extending the date of completion by one hundred and twenty-two (122) days. [Div. of Water Quality, Martin]

 

 

Summary

Authorization to approve Final Adjusting Change Order No. 4 to Judy Construction Company decreasing the cost of the Lower Cane Run Wet Weather Storage Project by $700,259.43 from $12,078,360.00 to $11,378,100.57 and extending the contract completion date by 122 days. (L01021-18) (Martin)

Budgetary Implications [select]: Yes

Advance Document Review:

Law: { Yes, Completed by [Michael Cravens, 9/20/18]}

Risk Management:  {No}

Fully Budgeted [select]: Yes

Account Number:                     4003-303408-3466-92811

This Fiscal Year Impact:                     -$700,259.43

Annual Impact:                      $

Project:  LCRWWSTNK_2014

Activity: CONSENT_DE

Budget Reference: 2014

Current Balance:

Body

BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:

                     Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute Change Order No. 4 (FINAL), which is attached hereto and incorporated herein by reference, to the Agreement with Judy Construction Company, for the Lower Cane Run Wet Weather Storage Facility Project, decreasing the Contract price by the sum of $700,259.43, from $12,078,360.00 to $11,378,100.57, and extending the date of completion by one hundred and twenty-two (122) days.

                     Section 2 - That this Resolution shall become effective on the date of its passage.