A Resolution authorizing the Mayor, on behalf of the Urban County Government, to execute an Engineering Services Agreement (awarded pursuant to RFP No. 41-2017) with Hazen & Sawyer, P.S.C., for investigation, design, and construction inspection services for the West Hickman Waste Water Treatment Plant Final Clarifiers #7 and #8 Structural Repair Project, at a cost estimated not to exceed $179,835. [Div. of Water Quality, Martin]
Summary
Authorization to execute an Agreement with Hazen and Sawyer for defined investigation, design services and construction administration for West Hickman WWTP Final Clarifiers #7 and #8 Structural Repair Design/Construction Inspection, as defined by RFP #41-201, the Budget for the base project is $179,835.00. Funds are Budgeted. (L1399-17) (Martin/Hoskins-Squier)
Budgetary Implications [select]: Yes
Advance Document Review:
Law: { Select Yes, Completed by [Michael Cravens, 12/14/17]}
Risk Management: {Select No)
Fully Budgeted [select]: Yes
Account Number: 4002-303403-0001-91017
This Fiscal Year Impact: $179,835.00
Annual Impact: $
Project:
Activity:
Budget Reference:
Current Balance: $235,954.19
Body
BE IT RESOLVED BY THE COUNCIL OF THE LEXINGTON-FAYETTE URBAN COUNTY GOVERNMENT:
Section 1 - That the Mayor, on behalf of the Lexington-Fayette Urban County Government, be and hereby is authorized to execute the Engineering Services Agreement (awarded pursuant to RFP No. 41-2017), which is attached hereto and incorporated herein by reference, with Hazen & Sawyer, P.S.C., for Investigation, Design, and Construction Inspection Services for the West Hickman Waste Water Treatment Plant Final Clarifiers #7 and #8 Structural Repair Project.
Section 2 - That an amount, estimated not to exceed the sum of $179,835.00, be and hereby is approved for payment to Hazen & Sawyer, P.S.C., from account #4002 - 303403 - 91017, pursuant to the terms of the Engineering Services Agreement.
Section 3 - That this Resolution shall become ef...